Project Description:
ATTLEBORO- RAMP RECONSTRUCTION & REALIGNMENT, FROM ROUTE I-95 (SB) TO ROUTE I-295 (SB)
This project is intended to improve vehicular safety at the ramp from I-95 SB to I-195 SB in Attleboro. This location has a high incidence of truck rollovers. Reconstruction and realignment of the ramp is proposed to address geometric deficiencies.
Location:
  • City of Attleboro
  • Resident Engineer: Brian Lewis
    Construction Contract Value: $6,056,345.94
    Construction Bid Price: $5,182,521.90
    Initial Construction Estimate: $4,839,000.00
    District: District 5

    Contracts (4) Progress
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 71613 -- Design -- Bridge Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for bridge, traffic and utility permit structural design and analysis assignments. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 84977 -- Construction Contract
    Ramp Reconstruction and Related Work (Including Bridge Repairs) Interstate 95 SB to Interstate 295 SB Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/20/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2012
    Project Initiation Form PIF Entered 02/24/2012
    Project Initiation Form PRC Submitted 02/24/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 09/13/2014
    Project Management
    100% Design 100% Package Received 07/07/2014
    100% Design 100% Package Comments to DE 07/18/2014
    25% Design 25% Package Received 03/05/2013
    25% Design 25% Package Comments to DE 06/20/2013
    25% Design Design Public Hearing 05/22/2014
    75% Design 75% Package Received 07/07/2014
    Final Design PS&E Received 08/15/2014
    Final Design PS&E to FAPRO 08/18/2014