| Project Description: |
BOSTON- BRIDGE REHABILITATION ALONG I-90, B-16-060 (STR 39), I-90 (WB & EB), OVER NORTH BEACON STREET
Replace deck, bearings, resurface approaches, repair structural steel, clean and paint superstructure, rehab substructure. (May be merged into 606762)
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Robert P Antico![]() |
| Estimated Total Contract Cost: | $4,830,000.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 6 |
| Current Status: | Design Public Hearing (as of 11/10/2015 ) |
|
Bridges
|
||||||||||||||
|
|
|
|||||||||||||||||||||||