Project Description:
NEWTON- BRIDGE REHABILITATION ALONG I-90, N-12-065, RAMPS A & B, STRUCTURE L-50 OVER CHARLES RIVER
Replace deck, bearings, approach sidewalk, resurface approaches, repair structural steel, clean and paint superstructure, rehab substructure.
Location:
  • City of Newton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Robert P Antico
    Estimated Total Contract Cost: $17,944,355.65
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: 75% Package Received (as of 01/29/2016 )

    Contracts (1) Progress
    # 77850 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/27/2012
    Project Initiation Form PIF Entered 02/27/2012
    Project Initiation Form PRC Submitted 07/14/2014
    Project Review Committee PRC Approved 03/26/2012
    Project Management
    25% Design 25% Package Received 04/21/2015
    25% Design 25% Package Comments to DE 06/26/2015
    25% Design 25% Package Comments to DE 11/16/2015
    25% Design 25% Package Approved 09/23/2015
    25% Design Design Public Hearing 11/10/2015
    75% Design 75% Package Received 01/29/2016