Project Description: |
NEWTON- BRIDGE REHABILITATION, N-12-027 ROUTE 16 (WASHINGTON STREET) OVER I-90, MBTA/CSX
Str 16 - Replace deck, bearings, resurface approaches, repair structural steel, clean and paint superstructure, rehab substructure. Str 16A - Rehab approach sidewalk and railing.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | William Henry Conroy |
Estimated Total Contract Cost: | $6,555,000.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 6 |
Current Status: | 25% Package Comments to DE (as of 02/19/2016 ) |
|
Bridges
|
|
|
|