Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BRIDGEWATER- BROCKTON- WEST BRIDGEWATER- INSTALLATION OF AN ANTI-GLARE SCREEN ALONG ROUTE 24 MEDIAN
Work on this project consists of installing an anti-glare screen on the median barrier to reduce vehicular headlight glare.
Location:
  • Town of Bridgewater
  • City of Brockton
  • Town of West Bridgewater
  • Resident Engineer: Peter Benkart
    Construction Contract Value: $1,135,288.00
    Construction Bid Price: $988,134.68
    Initial Construction Estimate: $956,860.00
    District: District 5

    Contracts (1) Progress
    # 75229 -- Construction Contract
    Installation of Anti-Glare Screen along Route 24 Median. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/23/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/28/2012
    Project Initiation Form PIF Entered 02/28/2012
    Project Initiation Form PRC Submitted 02/28/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 08/25/2012
    Project Management
    100% Design 100% Package Received 08/17/2012
    100% Design 100% Package Comments to DE 08/01/2012
    25% Design 25% Package Received 07/05/2012
    75% Design 75% Package Received 07/05/2012
    75% Design 75% Package Comments to DE 07/20/2012
    Final Design PS&E Received 08/20/2012
    Final Design PS&E to FAPRO 08/21/2012