Project Description: |
NEWTON- STEEL SUPERSTRUCTURE CLEANING (FULL REMOVAL) AND PAINTING OF 5 BRIDGES: N-12-017, N-12-020, N-12-026, N-12-069 AND N-12-070 ALONG I-90
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | MassDOT |
Project Manager: | Alyson Bedard![]() |
Estimated Total Contract Cost: | $4,577,754.25 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 6 |
Current Status: | Final Package to FAPRO (as of 07/21/2016 ) |
|