Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CUMMINGTON- RETAINING WALL REPLACEMENT ON ROUTE 9 ADJACENT TO SWIFT RIVER
This project proposes to completely replace a metal bin type retaining wall that provides structural support for Route 9. The project begins approximately 1000 feet west of the Goshen town line. The existing retaining wall is 450 feet in length and varies in height from 17 to 22 feet. There is settlement in the roadway along the top of wall; the proposed project will include full-depth roadway reconstruction, as well as wall replacement.
Location:
  • Town of Cummington
  • Construction Begins: Autumn 2023
    Resident Engineer: Michael Cullett
    Construction Bid Price: $3,850,818.00
    District: District 1

    Contracts (1) Progress
    # 123400 -- Construction Contract
    Retaining Wall Replacement on Route 9 adjacent to Swift River 10% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/02/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/28/2012
    Project Initiation Form PIF Entered 03/05/2012
    Project Initiation Form PRC Submitted 03/14/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 07/29/2023
    Project Management
    100% Design 100% Package Received 03/31/2023
    25% Design 25% Package Received 03/23/2022
    75% Design 75% Package Received 03/23/2022
    75% Design 75% Package Comments to DE 04/25/2022
    75% Design 75% Package Received - Resub 1 12/09/2022
    Final Design PS&E Received 05/11/2023