| Project Description: |
BOSTON- BRIDGE REHABILITATION, B-16-355, B-16-356 & B-16-366 AT INTERCHANGE 18
Str 104A & 104B - Deck and bearing device replacement, pier cap concrete repairs and slope paving rip/rap repairs. Str 105 - Cleaning and painting structural steel, bearing device replacement, and miscellaneous substructure repairs including slope paving rip/rap repairs.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Shu Tan![]() |
| Estimated Total Contract Cost: | $5,290,000.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 6 |
| Current Status: | This project is in the preliminary design phase. |
|