Project Description: |
BOSTON- BRIDGE REHABILITATION, B-16-060, NORTH BEACON STREET
Str 35 - Concrete parapet repairs, bridge railing and lighting repairs. Str 37 - Cleaning and painting structural steel, repair/replacement of connection plates, gussets and angles, concrete encasement repairs and lighting replacement. Str 38 - Cleaning and painting of structural steel, miscellaneous utility repairs, concrete encasement repairs and lighting replacement. (May be merged into 606762)
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Thomas P Donald |
Estimated Total Contract Cost: | $2,530,000.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 6 |
Current Status: | This project is in the preliminary design phase. |
|