| Project Description: |
BOSTON- CHELSEA- BARRIER REPAIR ALONG ROUTE 1, FROM TOBIN BRIDGE TO REVERE C.L. & ROUTE 1A IN EAST BOSTON AT LOGAN AIRPORT INTERCHANGE (NB) TO ADDISON STREET
This project will involve the replacement of barrier along Route 1 in Chelsea and along Route 1A in East Boston from Logan Airport Interchange northbound to Addison Street
|
| Location: |
|
| Resident Engineer: | Gene Lee![]() |
| Construction Contract Value: | $2,277,643.50 |
| Construction Bid Price: | $1,926,385.00 |
| Initial Construction Estimate: | $2,512,715.00 |
| District: | District 6 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||