Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- CANA ELECTRICAL SYSTEM UPGRADES, PLC CONTROL UPGRADES AND FACILITY IMPROVEMENTS
CANA programmable logic controller (PLC) controls and facilities improvements
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2022/2023
    Project Manager: John Czach
    Estimated Total Contract Cost: $61,061,695.80
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: 25% Package Comments to DE (as of 03/09/2021 )

    Contracts (2) Progress
    # 77857 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77866 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/01/2012
    Project Initiation Form PIF Entered 03/01/2012
    Project Initiation Form PRC Submitted 03/26/2012
    Project Review Committee PRC Approved 03/26/2012
    Project Management
    25% Design 25% Package Received 12/18/2020
    25% Design 25% Package Comments to DE 03/09/2021