Project Description:
BOSTON- CANA TUNNEL AND VENT BUILDING REHABILITATION
CANA TUNNEL (SB & NB), VENT BUILDINGS 14 & 15, STORM WATER PUMP STATION REHABILITATION, ELECTRICAL SYSTEM UPGRADES, PLC CONTROL UPGRADES AND FACILITY IMPROVEMENTS.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2025/2026
    Project Manager: Hema P Bhatt
    Estimated Total Contract Cost: $65,572,187.41
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: 75% Package Comments to DE (as of 08/24/2023 )

    Contracts (2) Progress
    # 77857 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77866 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/01/2012
    Project Initiation Form PIF Entered 03/01/2012
    Project Initiation Form PRC Submitted 03/26/2012
    Project Review Committee PRC Approved 03/26/2012
    Project Management
    25% Design 25% Package Received 12/18/2020
    25% Design 25% Package Comments to DE 03/09/2021
    75% Design 75% Package Received 06/23/2023
    75% Design 75% Package Comments to DE 08/24/2023