Project Description:
ARLINGTON- BIKEWAY CONNECTION AT INTERSECTION ROUTE 3 & ROUTE 60, MASSACHUSETTS AVENUE, PLEASANT STREET & MYSTIC STREET
The Arlington Center Safe Travel Project will provide a vital link in the Minuteman Bikeway, an 11-mile bikeway connecting Cambridge with Arlington, Lexington, and Bedford. In addition to connecting the two legs of the Minuteman Bikeway, traffic operations and safety and pedestrian safety in the Arlington Center area will be improved through additional advance signing, and upgrades to signal equipment, phasing, and timing at the intersection of Massachusetts Avenue/Mystic Street/Pleasant Street. Retiming and coordinating the intersections at Chestnut Street and Medford Street and increasing storage length on Mystic Street southbound at Massachusetts Avenue are also included.
Location:
  • Town of Arlington
  • Resident Engineer: Youssef Aboelsaad
    Construction Contract Value: $1,975,760.88
    Construction Bid Price: $1,640,269.90
    Initial Construction Estimate: $1,479,000.00
    District: District 4

    Contracts (2) Progress
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 84983 -- Construction Contract
    Bikeway Connection and Intersection Improvements (Including Signals) at Routes 3/2A and 60 (Massachusetts Avenue, Pleasant and Mystic Streets) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/24/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2012
    Project Initiation Form PIF Entered 03/02/2012
    Project Initiation Form PRC Submitted 03/05/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 09/13/2014
    Project Management
    100% Design 100% Package Received 03/04/2014
    100% Design 100% Package Comments to DE 06/26/2014
    25% Design 25% Package Received 12/07/2012
    25% Design 25% Package Comments to DE 12/18/2013
    25% Design Design Public Hearing 04/23/2013
    75% Design 75% Package Received 03/04/2014
    Final Design PS&E Received 09/08/2014