MONTGOMERY- RUSSELL- BRIDGE PRESERVATION, M-30-008=R-13-018 (4GT), I-90 OVER US 20, WESTFIELD RIVER & CSX RR
The proposed work for this project shall consist of repairs in the deck truss spans (spans 6 and 7) of the bridge. The deck truss repairs include replacing plates in various areas of the top and bottom chords, diagonals, and vertical posts. The repairs will also include gusset plate reinforcing as well as the replacement of rivets with high strength bolts in the location of the repairs. All proposed members will be primed and painted and the existing connecting surfaces will be cleaned and painted.
Location:
  • Town of Montgomery
  • Town of Russell
  • Construction Begins: Spring 2020
    Resident Engineer: Nicholas Gray
    Construction Bid Price: $46,973,440.00
    District: District 1

    Contracts (5) Progress
    # 108890 -- Construction Contract
    Bridge Structural Repairs and Related Work (Including Painting) Br. No. M-30-008=R-13-018 (Steel) Interstate 90 over US Route 20, Westfield River and the CSX Railroad
    # 57732 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects, includes ABP projects Final
    # 64317 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77879 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80661 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

    Contract Dates
    Notice to Proceed: 03/23/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2012
    Project Initiation Form PIF Entered 03/02/2012
    Project Initiation Form PRC Submitted 03/09/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 07/20/2019
    Project Management
    100% Design 100% Package Received 02/22/2019
    25% Design 25% Package Received 06/27/2016
    75% Design 75% Package Received 02/09/2018
    Final Design PS&E Received 05/21/2019
    Final Design PS&E to FAPRO 07/09/2019