Project Description:
WORCESTER- BLACKSTONE CANAL STREETSCAPE IMPROVEMENTS ON HARDING STREET
Proposed improvements include resurfacing, reconstructed sidewalks, and streetscape improvements to highlight historic elements of the Blackstone Canal District.
Location:
  • City of Worcester
  • Construction Begins: Summer 2018
    Resident Engineer: Anthony Maglione
    Construction Bid Price: $1,729,900.00
    District: District 3

    Contracts (1) Progress
    # 103065 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Harding Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/17/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2012
    Project Initiation Form PIF Entered 03/06/2012
    Project Initiation Form PRC Submitted 03/13/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 12/23/2017
    Project Management
    100% Design 100% Package Received 01/23/2017
    100% Design 100% Package Comments to DE 03/13/2017
    25% Design 25% Package Received 12/18/2012
    25% Design 25% Package Received 01/12/2015
    25% Design 25% Package Comments to DE 03/24/2015
    25% Design 25% Package Comments to DE 01/27/2016
    25% Design Design Public Hearing 02/04/2014
    25% Design Design Public Hearing 03/29/2016
    75% Design 75% Package Received 01/23/2017
    75% Design 75% Package Comments to DE 03/13/2017
    Final Design PS&E Received 09/22/2017
    Final Design PS&E to Peer Reviewer 10/04/2017
    Final Design Peer Review Comments to DE 10/31/2017
    Final Design PS&E to FAPRO 12/11/2017