Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- IMPROVEMENTS ALONG GAINSBOROUGH AND ST. BOTOLPH STREETS
This project will improve the pedestrian and bicycle activity as part of the construction of new buildings for the New England Conservancy.
Location:
  • City of Boston
  • Resident Engineer: Jahangir Rajabi Dehkharghani
    Construction Bid Price: $3,701,174.00
    District: District 6

    Contracts (1) Progress
    # 88630 -- Construction Contract
    Streetscape Improvements and Related Work along Gainsborough and St. Botolph Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/11/2015
    Contract Information
    Project Designer: Other
    Funding Source: TRANS. INITIATIVE EARMARK
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2012
    Project Initiation Form PIF Entered 03/07/2012
    Project Initiation Form PRC Submitted 03/16/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 06/20/2015
    Project Management
    100% Design 100% Package Received 06/27/2014
    100% Design 100% Package Comments to DE 08/13/2014
    25% Design 25% Package Received 09/19/2013
    25% Design 25% Package Comments to DE 11/21/2013
    25% Design 25% Package Approved 04/17/2014
    25% Design Design Public Hearing 04/16/2014
    25% Design 25% Plans Complete 03/07/2014
    Final Design PS&E Received 06/12/2015
    Final Design PS&E to FAPRO 06/17/2015