ADAMS- NORTH ADAMS- ASHUWILLTICOOK RAIL TRAIL EXTENSION TO ROUTE 8A (HODGES CROSS ROAD)
This project proposes to extend the Ashuwillticook Rail Trail from Lime Street in Adams to Hodges Cross Road in North Adams; a distance of approximately 1.8 miles. The proposed route would be off-road, traversing agricultural land.
Location:
  • Town of Adams
  • City of North Adams
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2028
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $7,946,500.00
    Estimated Total Federal Participating Construction Cost: $8,220,000.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 11/26/2019 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: ADAMS
    NORTH ADAMS
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $7,365,120.00
    State Cost: $1,841,280.00
    Total Cost: $9,206,400.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/09/2012
    Project Initiation Form PIF Entered 03/09/2012
    Project Initiation Form PRC Submitted 07/19/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Management
    Consultant Contract Process NTP Issued 11/26/2019