Project Description:
LANESBOROUGH- PITTSFIELD- ASHUWILLTICOOK RAIL TRAIL EXTENSION TO CRANE AVENUE
This project would utilize an existing Right of Way owned by the Housatonic RR, to be sold to the City under a transportation lease agreement with MassDOT. The project would convert 1.5 miles of track into a 10-ft wide paved bike-path, with a cross-section consistent with the rest of the rail-trail to the north. The project would connect the popular Ashuwillticook rail-trail to the region’s largest municipality, in an area of Pittsfield which has the highest density of commercial/retail businesses in the County.
Location:
  • Town of Lanesborough
  • City of Pittsfield
  • Construction Begins: Autumn 2020
    Resident Engineer: John Tietgens
    Construction Bid Price: $2,249,421.85
    District: District 1

    Contracts (1) Progress
    # 112876 -- Construction Contract
    Construction of the Ashuwillticook Bikeway Rail Trail Extension to Crane Avenue Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/15/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/09/2012
    Project Initiation Form PIF Entered 07/19/2012
    Project Initiation Form PRC Submitted 07/19/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 09/12/2020
    Project Management
    100% Design 100% Package Received 06/04/2018
    100% Design 100% Package Comments to DE 10/05/2018
    100% Design 100% Package Received - Resub 1 02/28/2019
    25% Design 25% Package Received 03/06/2015
    25% Design 25% Package Received 11/23/2015
    25% Design 25% Package Received 12/31/2015
    25% Design 25% Package Comments to DE 08/26/2015
    25% Design Design Public Hearing 04/12/2016
    75% Design 75% Package Received 09/08/2017
    75% Design 75% Package Comments to DE 01/02/2018
    Final Design PS&E Received 05/08/2019
    Final Design PS&E Received - Resub 1 08/05/2019
    Final Design PS&E Received - Resub 2 01/29/2020
    Final Design PS&E Received - Resub 3 07/22/2020
    Final Design PS&E Received - Resub 4 08/10/2020