Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 4- SCHEDULED BRIDGE MAINTENANCE REPAIRS ON L-010-015 & L-15-086 (NB/SB)
Repairs to these structurally deficient bridge elements to bring them out of the structurally deficient list. These bridges are either not in any program or are in a program where the funding source is not known.
Location:
Resident Engineer: William Murphy
Construction Contract Value: $2,406,685.00
Construction Bid Price: $1,983,350.00
Initial Construction Estimate: $1,670,900.00
District: District 4

Contracts (1) Progress
# 75582 -- Construction Contract
Bridge Repairs and Related Work (Including Painting) (L-10-015) - Grove Street over Interstate 95 and (L-15-086) (NB & SB) Interstate 495 over the MBTA and B & M Railroads. Completed

Bridges

Contract Dates
Notice to Proceed: 03/01/2013
Contract Information
Project Designer: In-House Boston
Funding Source: BRR OFF SYSTEM
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 03/14/2012
Project Initiation Form PIF Entered 03/14/2012
Project Initiation Form PRC Submitted 03/14/2012
Project Review Committee PRC Approved 03/22/2012
Project Status Advertised 09/15/2012
Project Management
100% Design 100% Package Received 07/03/2012
Final Design PS&E Received 09/01/2012
Final Design PS&E to FAPRO 09/05/2012