Project Description:
BOURNE- TRAFFIC AND MULTI-MODAL IMPROVEMENTS @ BELMONT CIRCLE AT ROUTES 6/25/28
This project is intended as an interim improvement to address safety and congestion issues at Belmont Circle. Proposed improvements include upgraded pavement markings and signs, as well as improved pedestrian and bicycle through the installation of sidewalks and shared use paths.
Location:
  • Town of Bourne
  • Construction Begins: Summer 2020
    Resident Engineer: Ian Bettencourt
    Construction Bid Price: $4,395,731.20
    District: District 5

    Contracts (3) Progress
    # 111594 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) at Belmont Circle (Routes 6, 25 & 28) Completed
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/10/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/20/2012
    Project Initiation Form PIF Entered 07/13/2012
    Project Initiation Form PRC Submitted 07/13/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 06/13/2020
    Project Management
    100% Design 100% Package Received 12/17/2019
    25% Design 25% Package Received 08/09/2017
    25% Design 25% Package Comments to DE 12/18/2017
    25% Design Design Public Hearing 08/15/2018
    75% Design 75% Package Received 02/17/2019
    75% Design 75% Package Comments to DE 06/06/2019
    Final Design PS&E Received 03/12/2020
    Final Design PS&E Received - Resub 1 05/12/2020