Project Description:
BOSTON- BRIDGE REPLACEMENT, B-16-109, RIVER STREET BRIDGE OVER MBTA/AMTRAK
This project involves modification of the substructure and replacement of the truss with a through-girder superstructure.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2024/2025
    Project Manager: Kathy Dougherty
    Estimated Total Contract Cost: $11,431,100.00
    Estimated Total Federal Participating Construction Cost: $12,538,835.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: Design Public Hearing (as of 05/03/2023 )

    Contracts (2) Progress
    # 115761 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77860 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $12,538,835 (NGBP - Next Gen Bridge Program)
  • Category FA - Next Generation Bridge GANs
    Federal Cost: $10,031,068.00
    State Cost: $2,507,767.00
    Total Cost: $12,538,835.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/20/2012
    Project Initiation Form PIF Entered 03/20/2012
    Project Initiation Form PRC Submitted 03/20/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Management
    25% Design 25% Package Received 10/28/2019
    25% Design 25% Package Comments to DE 02/21/2020
    25% Design 25% Package Approved 12/15/2022
    25% Design 25% Package Received - Resub 1 08/31/2020
    25% Design 25% Package Received - Resub 2 03/02/2021
    25% Design 25% Package Received - Resub 3 11/17/2021
    25% Design 25% Package Received - Resub 4 02/22/2022
    25% Design 25% Package Received - Resub 5 09/30/2022
    25% Design Design Public Hearing 05/03/2023