Project Description:
BOSTON- BRIDGE REPLACEMENT, B-16-181, WEST ROXBURY PARKWAY OVER MBTA
The proposed project consists of the replacement of the existing Arthur J. Lewis Bridge superstructure and rehabilitation of the bridge substructure carrying West Roxbury Parkway utilizing accelerated bridge construction methods. The bridge spans the MBTA commuter rail Needham Line between the Holy Name Rotary and Belgrade Avenue. Bicycle accommodation consisting of 5’ buffered bicycle lanes have been provided in accordance with applicable design guides.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2024/2025
    Project Manager: Anthony Christakis
    Estimated Total Contract Cost: $9,547,492.35
    Estimated Total Federal Participating Construction Cost: $11,365,746.27
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 08/03/2024 )

    Contracts (2) Progress
    # 115745 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $8,889,831 (HIP-BR)
  • Increase to 10,382,603 via STIP Action 9.
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $8,306,082.40
    State Cost: $2,076,520.60
    Total Cost: $10,382,603.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/20/2012
    Project Initiation Form PIF Entered 03/20/2012
    Project Initiation Form PRC Submitted 03/20/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 08/03/2024
    Project Management
    100% Design 100% Package Received 08/28/2023
    100% Design 100% Package Comments to DE 10/02/2023
    25% Design 25% Package Received 07/11/2022
    25% Design 25% Package Received - Resub 1 01/25/2023
    25% Design Design Public Hearing 01/11/2023
    75% Design 75% Package Received 05/19/2023
    Final Design PS&E Received 11/28/2023