Project Description:
HOLYOKE- SIGNAL INSTALLATION & IMPROVEMENTS ON CHERRY STREET @ I-91 (INTERCHANGE 16)
Following a Road Safety Audit this project is expected to include the installation of two new traffic signals, one at the intersection of the I-91 SB off ramp and Cherry Street and one at the intersection of I-91 NB off ramp and Cherry Street. Other improvements may include new pavement markings and signage.
Location:
  • City of Holyoke
  • Resident Engineer: Jessica Gaudet
    Construction Contract Value: $1,379,557.00
    Construction Bid Price: $1,197,066.00
    Initial Construction Estimate: $1,101,610.00
    District: District 2

    Contracts (1) Progress
    # 79878 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) along a Section of Cherry Street (Route 202) and Ramps for Interstate 91. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/20/2012
    Project Initiation Form PIF Entered 03/20/2012
    Project Initiation Form PRC Submitted 03/20/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 09/21/2013
    Project Management
    100% Design 100% Package Received 08/19/2013
    100% Design 100% Package Comments to DE 09/03/2013
    25% Design 25% Package Received 06/03/2013
    25% Design Design Public Hearing 08/15/2013
    75% Design 75% Package Received 08/19/2013
    75% Design 75% Package Comments to DE 09/03/2013
    Final Design PS&E Received 09/06/2013
    Final Design PS&E to FAPRO 09/11/2013