Project Description:
PITTSFIELD- SAFE ROUTES TO SCHOOL (CONTE COMMUNITY SCHOOL)
The proposed project consists of converting the existing 2-way Atlantic Street/South Atlantic Street (from West Union Street to Linden Street) to a one-way street (southbound) in order to construct a new sidewalk along its west side. The street will be 20 feet wide, and will include shared lane signing in accordance with applicable design guides. The proposed sidewalk will extend from West Union Street to Station 61+75 on Summit Avenue. Additional improvements will include providing a pavement overlay as well as drainage improvements. ADA-compliant wheelchair ramps as well as MUTCD-compliant pavement markings, and signage will also be provided.
Location:
  • City of Pittsfield
  • Resident Engineer: Zahid Pervaiz
    Construction Contract Value: $491,277.90
    Construction Bid Price: $409,903.06
    Initial Construction Estimate: $439,605.00
    District: District 1

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 79728 -- Construction Contract
    Sidewalk Construction along Sections of Summit Avenue, Atlantic and South Atlantic Streets (Safe Routes to Conte Memorial School) . Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2012
    Project Initiation Form PIF Entered 03/21/2012
    Project Initiation Form PRC Submitted 03/21/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 09/14/2013
    Project Management
    100% Design 100% Package Received 04/17/2013
    100% Design 100% Package Comments to DE 05/30/2013
    25% Design 25% Package Received 08/27/2012
    25% Design 25% Package Comments to DE 11/07/2012
    25% Design Design Public Hearing 01/15/2013
    75% Design 75% Package Received 08/27/2012
    75% Design 75% Package Comments to DE 11/07/2012
    Final Design PS&E Received 07/08/2013
    Final Design PS&E to FAPRO 08/14/2013