Project Description:
NEW BEDFORD- CORRIDOR IMPROVEMENTS AND RELATED WORK ON COGGESHALL STREET, FROM PURCHASE STREET TO MITCHELL AVENUE
This project is intended to address poor pavement quality, traffic safety issues and the lack of multi-modal accommodation along the corridor. Work consists of roadway improvements, traffic signal upgrades and coordination along the corridor as well as improved accommodation for bicycles and pedestrians. Drainage will be upgraded along with the installation of new signage and pavement markings.
Location:
  • City of New Bedford
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Matthew Lambert
    Construction Bid Price: $3,847,368.10
    District: District 5

    Contracts (1) Progress
    # 96791 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) along a Section of Coggeshall Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/22/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/22/2012
    Project Initiation Form PIF Entered 06/27/2012
    Project Initiation Form PRC Submitted 06/29/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 08/06/2016
    Project Management
    100% Design 100% Package Received 05/12/2016
    100% Design 100% Package Comments to DE 06/15/2016
    25% Design 25% Package Received 04/16/2014
    25% Design 25% Package Comments to DE 04/01/2015
    25% Design Design Public Hearing 07/08/2015
    75% Design 75% Package Received 11/11/2015
    75% Design 75% Package Comments to DE 02/24/2016
    Final Design PS&E Received 07/26/2016
    Final Design PS&E to FAPRO 08/01/2016