Project Description:
MONROE- ROWE- SUPERSTRUCTURE REPLACEMENT, M-26-002=R-10-002, DEPOT STREET OVER THE DEERFIELD RIVER
This municipally owned, weathering steel truss is both structurally deficient and functionally obsolete. Constructed in 1992, a posted 3-ton weight restriction severely limits vehicle usage, especially emergency services, between Rowe and Monroe. Complete closure of the bridge would result in a 19 mile detour. The bridge, a single span structure spanning 148 feet, currently carries two-way traffic with a curb to curb width of 24 feet. There is an existing sidewalk on the north side, outside of the truss. Current AASHTO Rating is 5 (deck) – 3 (superstructure) – 6 (substructure/abutments). It is currently envisioned that the proposed project would replace the superstructure only, however, if a heavier replacement structure is required, then additional substructure work would also be included.
Location:
  • Town of Monroe
  • Town of Rowe
  • Resident Engineer: Stephen Eddington
    Construction Contract Value: $2,166,249.00
    Construction Bid Price: $1,895,340.00
    Initial Construction Estimate: $2,753,693.70
    District: District 1

    Contracts (3) Progress
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 79507 -- Construction Contract
    Bridge Superstructure Replacement (M-26-002=R-10-002) (Steel) - Depot Street over the Deerfield River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2012
    Project Initiation Form PIF Entered 03/28/2012
    Project Initiation Form PRC Submitted 03/28/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 08/31/2013
    Project Management
    100% Design 100% Package Received 08/12/2013
    25% Design 25% Package Received 01/15/2013
    25% Design 25% Package Comments to DE 01/04/2013
    25% Design 25% Package Comments to DE 01/10/2013
    25% Design Design Public Hearing 03/12/2013
    75% Design 75% Package Received 05/24/2013
    75% Design 75% Package Comments to DE 06/24/2013
    Final Design PS&E Received 09/03/2013
    Final Design PS&E to FAPRO 08/28/2013