Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WORTHINGTON- RECONSTRUCTION & RELATED WORK ON ROUTE 143 (PHASE I) COLD STREET TO CHESTERFIELD TOWN LINE
The Town is seeking to mill and overlay the eastern 2.2 miles of Route 143 (Williamsburg Road) at its current width of 28 ft +/-. Proposed improvements for the remaining 5.3 miles of Route 143 (Old North Road) include reclamation and box widening to 26 feet to provide improved accommodation for all users, cutting back slopes to improve sight distance at several horizontal curves, selected drainage system improvements, guard rail, and new signs and pavement markings.
Location:
  • Town of Worthington
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Justin Bourbeau
    Construction Bid Price: $7,284,365.00
    District: District 1

    Contracts (1) Progress
    # 108889 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 143 (Old North & Williamsburg Roads) (Phase 1) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/10/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Received 01/24/2012
    Project Need Form PNF Entered 03/29/2012
    Project Need Form PNF Approved 03/28/2012
    Project Initiation Form PIF Entered 11/08/2012
    Project Initiation Form PRC Submitted 11/08/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 07/20/2019
    Project Management
    100% Design 100% Package Received 10/15/2018
    100% Design 100% Package Comments to DE 11/20/2018
    100% Design 100% Package Received - Resub 1 03/04/2019
    25% Design 25% Package Received 05/18/2015
    25% Design 25% Package Comments to DE 08/03/2015
    25% Design Design Public Hearing 04/07/2016
    75% Design 75% Package Received 05/01/2017
    75% Design 75% Package Comments to DE 10/17/2017
    Final Design PS&E Received 06/26/2019
    Final Design PS&E to FAPRO 07/08/2019