Project Description:
STATEWIDE- REPLACEMENT OF VARIABLE MESSAGE SIGNS (VMS)
Replacement of non-operational permanent overhead Variable Message Signs at various locations statewide.
Location:
Construction Begins: Winter 2016/2017
Resident Engineer: Derek Coble
Construction Bid Price: $2,883,117.00
District: District 6

Contracts (1) Progress
# 97606 -- Construction Contract
Variable Message Sign Replacement and Improvements along Sections of Routes 2, 3, 24, 128 and Interstates 90, 93 & 95. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/01/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/29/2012
    Project Initiation Form PIF Entered 07/26/2012
    Project Initiation Form PRC Submitted 07/26/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 08/27/2016
    Project Management
    100% Design 100% Package Received 04/12/2016
    75% Design 75% Package Received 10/02/2015
    Final Design PS&E Received 08/10/2016
    Final Design PS&E to FAPRO 08/22/2016