| Project Description: |
BOSTON- SCHEDULED & EMERGENCY STRUCTURAL REPAIRS ON THE TOBIN BRIDGE
Scheduled and emergency structural repairs on the Tobin Bridge.
|
| Location: |
|
| Resident Engineer: | Gene Lee![]() |
| Construction Contract Value: | $724,243.00 |
| Construction Bid Price: | $281,950.60 |
| Initial Construction Estimate: | $302,450.00 |
| District: | District 6 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||