DISTRICT 6- SCHEDULED & EMERGENCY STRUCTURAL & SUBSTRUCTURE REPAIRS AT VARIOUS LOCATIONS
MHS, etc. - scheduled & emergency structural bridge repairs & substructure repairs at various locations. Project should include miscellaneous repairs to Central Artery and Boston Extension Bridges including bearing adjustments or replacement, superstructure and substructure repairs. This project should also include potential remediation of cracking in concrete viaducts including Ramp XX on I-93 and should include remediation of miscellaneous bridge repairs identified in the Stem to Stern report.
Location:
Resident Engineer: Gene Lee
Construction Contract Value: $11,965,078.40
Construction Bid Price: $2,195,678.00
Initial Construction Estimate: $2,485,707.50
District: District 6

Contracts (1) Progress
# 76734 -- Construction Contract
Scheduled and Emergency Bridge Structural and Substructural Repairs at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/07/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/04/2012
    Project Initiation Form PIF Entered 04/04/2012
    Project Initiation Form PRC Submitted 03/22/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 02/23/2013
    Project Management
    Final Design PS&E Received 01/22/2013
    Final Design PS&E to FAPRO 02/19/2013