DISTRICT 6- TREE TRIMMING & SIGHT DISTANCE IMPROVEMENT AT VARIOUS LOCATIONS
MHS - tree trimming & site distance improvement at various locations.
Location:
Construction Begins: Spring 2017
Resident Engineer: Timothy Fitzgerald
Construction Bid Price: $526,743.00
District: District 6

Contracts (1) Progress
# 98161 -- Construction Contract
Scheduled and Emergency Tree Trimming, Removal and Sight Distance Clearing at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/26/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/05/2012
    Project Initiation Form PIF Entered 04/05/2012
    Project Initiation Form PRC Submitted 03/22/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 10/01/2016
    Project Management
    Final Design PS&E Received 06/17/2016
    Final Design PS&E to FAPRO 09/09/2016