SHIRLEY- UXBRIDGE- WORCESTER- STORMWATER RETROFITS ON ROUTE 2, ROUTE 2A, ROUTE 146 AND ROUTE 122
This project will provide for upgrading stormwater infrastructure for impaired water bodies at specific locations throughout the District.
Location:
  • Town of Shirley
  • Town of Uxbridge
  • City of Worcester
  • Resident Engineer: Dariusz Wisniewski
    Construction Bid Price: $769,562.48
    District: District 3

    Contracts (1) Progress
    # 90315 -- Construction Contract
    Drainage Repairs and Improvements at 3 Locations on Routes 2A, 146 and 122. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/28/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/05/2012
    Project Initiation Form PIF Entered 07/26/2012
    Project Initiation Form PRC Submitted 07/26/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 08/22/2015
    Project Management
    100% Design 100% Package Received 05/15/2015
    100% Design 100% Package Comments to DE 07/17/2015
    25% Design Design Public Hearing 01/22/2015
    75% Design 75% Package Received 07/03/2014
    75% Design 75% Package Received 09/22/2014
    75% Design 75% Package Received 10/01/2014
    75% Design 75% Package Comments to DE 11/12/2014
    Final Design PS&E Received 08/10/2015
    Final Design PS&E to FAPRO 08/18/2015