| Project Description: | BOSTON- LEAK SEALING, FIREPROOFING & MISCELLANEOUS REPAIRS IN I-93, TIP O'NEILL TUNNEL (CRC 1E) I-93 Tunnel ceiling leak, fireproofing and miscellaneous repairs. | 
| Location: |  | 
| Resident Engineer: | Matthew Berg  | 
| Construction Contract Value: | $12,491,893.75 | 
| Construction Bid Price: | $10,845,125.00 | 
| Initial Construction Estimate: | $12,087,150.00 | 
| District: | District 6 | 
| 