Project Description:
DISTRICT 6- MISCELLANEOUS OVERHEAD SIGN REPAIRS IN TUNNELS
Structural repair or replacement of overhead signs and supports in MHS tunnels.
Location:
Construction Begins: Spring 2017
Resident Engineer: Michael McGonagle
Construction Bid Price: $796,566.00
District: District 6

Contracts (1) Progress
# 98156 -- Construction Contract
Fabrication and Installation of Tunnel Overhead Guide Signs along Sections of Interstates 90, 93 and Route 1 (Re-Advertised Project). Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/20/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/05/2012
    Project Initiation Form PIF Entered 04/09/2012
    Project Initiation Form PRC Submitted 03/22/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 02/06/2016
    Project Status Advertised 10/01/2016
    Project Management
    100% Design 100% Package Received 08/29/2016
    Final Design PS&E Received 09/08/2015
    Final Design PS&E to FAPRO 09/26/2016