Project Description:
CONCORD- BRIDGE PRESERVATION, C-19-014, OLD STOW ROAD OVER MBTA & B&M RR
CONCORD- BRIDGE PRESERVATION, C-19-014, OLD STOW ROAD OVER MBTA & B&M RR
Location:
  • Town of Concord
  • Resident Engineer: Jay Patel
    Construction Contract Value: $659,976.74
    Construction Bid Price: $435,342.00
    Initial Construction Estimate: $401,824.78
    District: District 4

    Contracts (3) Progress
    # 69360 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 69765 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77592 -- Construction Contract
    Bridge Deck and Substructure Repair Br. No. C-19-014 (Concrete) Old Stow Road over the MBTA Railroad. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/30/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/06/2012
    Project Initiation Form PIF Entered 04/06/2012
    Project Initiation Form PRC Submitted 10/03/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 05/18/2013
    Project Management
    100% Design 100% Package Received 01/11/2013
    100% Design 100% Package Comments to DE 02/19/2013
    Final Design PS&E Received 03/04/2013
    Final Design PS&E to FAPRO 05/15/2013
    Consultant Contract Process NTP Issued 11/07/2012
    Consultant Contract Process Workhours Approved 11/07/2012