Project Description:
DUDLEY- BRIDGE DEMOLITION, D-12-009, CARPENTER ROAD OVER QUINNEBAUG RAIL TRAIL
This timber bridge is a structurally deficient DOT Ch 634 bridge with an AASHTO = 16.2 and is posted for 6 tons. The bridge will be demolished and an at-grade pedestrian crossing will be constructed for the rail trail users.
Location:
  • Town of Dudley
  • Construction Begins: Spring 2017
    Resident Engineer: Peter Kurt
    Construction Bid Price: $413,113.70
    District: District 3

    Contracts (2) Progress
    # 77856 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 97685 -- Construction Contract
    Bridge Demolition Br. No. D-12-009 Carpenter Road over Quinebaug Rail Trail and Construction of an At-Grade Roadway. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/12/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/06/2012
    Project Initiation Form PIF Entered 04/06/2012
    Project Initiation Form PRC Submitted 07/25/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 09/03/2016
    Project Management
    100% Design 100% Package Received 03/29/2016
    100% Design 100% Package Comments to DE 04/29/2016
    25% Design 25% Package Received 04/15/2015
    25% Design 25% Package Comments to DE 07/17/2015
    25% Design 25% Package Approved 08/12/2015
    25% Design Design Public Hearing 11/19/2015
    25% Design 25% Plans Complete 08/12/2015
    75% Design 75% Package Received 12/21/2015
    Final Design PS&E Received 05/25/2016
    Final Design PS&E to Peer Reviewer 06/20/2016
    Final Design Peer Review Comments to DE 07/12/2016
    Final Design PS&E to FAPRO 08/30/2016
    Consultant Contract Process NTP Issued 05/12/2014