Project Description:
LANCASTER- BRIDGE REPLACEMENT, L-02-018, JACKSON ROAD OVER ROUTE 2
This functionally obsolete bridge has an AASHTO rating = 49.8. The vertical clearance over route 2 is insufficient at 14'-3" and has resulted in repeated collision damage. Replacement of the superstructure is proposed.
Location:
  • Town of Lancaster
  • Resident Engineer: Stephen Romano
    Construction Contract Value: $6,274,599.15
    Construction Bid Price: $5,346,444.00
    Initial Construction Estimate: $4,895,000.00
    District: District 3

    Contracts (7) Progress
    # 58994 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64326 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69755 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77848 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77873 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 85017 -- Construction Contract
    Bridge Replacement (Steel) Br. No. L-02-018 Jackson Road over Route 2 (George W. Stanton Highway) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/06/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/06/2012
    Project Initiation Form PIF Entered 04/06/2012
    Project Initiation Form PRC Submitted 07/25/2012
    Project Review Committee PRC Approved 12/21/2012
    Project Status Advertised 09/20/2014
    Project Management
    25% Design 25% Package Received 04/10/2014
    25% Design 25% Package Comments to DE 04/25/2014
    25% Design Design Public Hearing 07/24/2014
    75% Design 75% Package Received 08/06/2014
    75% Design 75% Package Comments to DE 08/29/2014
    Final Design PS&E Received 09/16/2014
    Final Design PS&E to FAPRO 09/16/2014
    Consultant Contract Process NTP Issued 05/15/2013