HUBBARDSTON- BRIDGE REPLACEMENT, H-24-009, EVERGREEN ROAD OVER MASON BROOK
This municipally owned structure is structurally deficient with an AASHTO = 43.4. The inspection rating is 6-4-5. It is proposed to replace the entire structure.
Location:
  • Town of Hubbardston
  • Construction Begins: Spring 2020
    Resident Engineer: Peter Kurt
    Construction Bid Price: $1,732,191.00
    District: District 3

    Contracts (2) Progress
    # 109676 -- Construction Contract
    Bridge Replacement Br. No. H-24-009 (Precast Concrete Arch) Evergreen Road over Mason Brook Completed
    # 77857 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/21/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/06/2012
    Project Initiation Form PIF Entered 04/06/2012
    Project Initiation Form PRC Submitted 07/25/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 09/14/2019
    Project Management
    100% Design 100% Package Received 05/17/2019
    100% Design 100% Package Comments to DE 06/17/2019
    100% Design 100% Plans Approved 07/12/2019
    100% Design 100% Plans Complete 07/12/2019
    25% Design 25% Package Received 08/01/2017
    25% Design 25% Package Comments to DE 10/06/2017
    25% Design 25% Package Approved 01/23/2019
    25% Design 25% Package Received - Resub 1 05/21/2018
    25% Design Design Public Hearing 10/16/2018
    25% Design 25% Plans Complete 10/17/2018
    75% Design 75% Package Received 02/12/2019
    75% Design 75% Package Comments to DE 03/28/2019
    75% Design 75% Plans Approved 04/03/2019
    75% Design 75% Plans Complete 04/03/2019
    Final Design PS&E Received 07/22/2019
    Final Design PS&E to FAPRO 08/30/2019