Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- LEAK SEALING, FIREPROOFING & MISCELLANEOUS REPAIRS IN MASSDOT TUNNELS
The work under this Contract consists of inspection, maintenance, and repair of elements of the Central Artery/Tunnel system. The majority of the work is related to the control of leaking elements of the tunnels, and repairs or maintenance to those elements that are deteriorated as a result of the leakage. Elements of the tunnel to be repaired or receive maintenance include slurry walls, roadway barriers, the roadway wearing surfaces, girders, soldier piles, coating systems, etc.
Location:
  • City of Boston
  • Construction Begins: Spring 2019
    Resident Engineer: Matthew Berg
    Construction Bid Price: $14,242,375.00
    District: District 6

    Contracts (2) Progress
    # 106084 -- Construction Contract
    Leak Sealing, Fireproofing and Miscellaneous Repairs (Including Painting) in the Central Artery Tunnel System along Interstates 90/93 (Ted Williams, Callahan & Sumner Tunnels) Completed
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/10/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/06/2012
    Project Initiation Form PIF Entered 04/10/2012
    Project Initiation Form PRC Submitted 03/22/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 09/29/2018
    Project Management
    100% Design 100% Package Received 05/17/2018
    75% Design 75% Package Received 03/05/2018
    Final Design PS&E Received 08/15/2018