Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SHREWSBURY- NORTHBOROUGH- WESTBOROUGH- RESURFACING AND RELATED WORK ON ROUTE 9
This project consists of resurfacing Route 9 in Shrewsbury, Northborough and Westborough from mile marker 100.3 to mile marker 107.0 for a total length of 6.7 miles.
Location:
  • Town of Northborough
  • Town of Shrewsbury
  • Town of Westborough
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Roger Wykes
    Construction Bid Price: $12,404,615.70
    District: District 3

    Contracts (1) Progress
    # 97595 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 9 (Boston-Worcester Turnpike). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/16/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/09/2012
    Project Initiation Form PIF Entered 04/13/2012
    Project Initiation Form PRC Submitted 04/13/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 08/27/2016
    Project Management
    100% Design 100% Package Received 06/20/2016
    100% Design 100% Package Comments to DE 07/29/2016
    25% Design 25% Package Received 06/16/2015
    25% Design 25% Package Received 04/13/2016
    25% Design 25% Package Comments to DE 09/01/2015
    75% Design 75% Package Received 06/16/2015
    75% Design 75% Package Received 04/13/2016
    75% Design 75% Package Comments to DE 04/21/2016
    Final Design PS&E Received 06/20/2016
    Final Design PS&E Received 08/17/2016
    Final Design PS&E to Peer Reviewer 06/20/2016
    Final Design Peer Review Comments to DE 07/29/2016
    Final Design PS&E to FAPRO 08/22/2016