AMHERST- PELHAM- RECONSTRUCTION OF AMHERST ROAD, FROM 800 FEET EAST OF ENFIELD ROAD TO ROUTE 202 (2.5 MILES - PHASE II)
The work to be done consists of minor realignment, widening and overlaying Amherst Road. The work includes earth excavation, coldplaning, full depth hot mix asphalt pavement, hot mix asphalt overlay, drainage, berm, highway guard, school speed limit sign beacons, signs, landscaping and other incidental work.
Location:
  • Town of Amherst
  • Town of Pelham
  • Resident Engineer: Victor LaMountain
    Construction Contract Value: $3,592,815.00
    Construction Bid Price: $3,147,000.00
    Initial Construction Estimate: $3,513,000.00
    District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 86120 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Amherst Road (Phase II). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/25/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/10/2012
    Project Initiation Form PIF Entered 04/10/2012
    Project Initiation Form PRC Submitted 04/10/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 12/20/2014
    Project Management
    100% Design 100% Package Received 11/02/2010
    100% Design 100% Package Received 04/28/2014
    100% Design 100% Package Comments to DE 12/20/2010
    100% Design 100% Package Comments to DE 06/17/2014
    25% Design Design Public Hearing 06/23/2011
    Final Design PS&E Received 10/03/2014
    Final Design PS&E to FAPRO 12/17/2014