Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SOMERVILLE- CAMBRIDGE- RECONSTRUCTION OF BEACON STREET, FROM OXFORD STREET TO CAMBRIDGE C.L.
This project consists of reconstructing Beacon Street from the Cambridge city line to Oxford Street, an estimated distance of 1.1 miles. New sidewalks, curbing, drainage and signal improvements are included in the project.
Location:
  • City of Cambridge
  • City of Somerville
  • Resident Engineer: John McGillicuddy
    Construction Bid Price: $9,550,337.97
    District: District 4

    Contracts (2) Progress
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 90025 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Beacon Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/24/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    MassDOT is receiving a number of e-mail, telephone and feedback inquiry comments in support and in opposition to the project. Comments have been forwarded to appropriate MassDOT Individuals and Sections, as well as to the City who is the project proponent and designer of this local roadway project
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/19/2012
    Project Initiation Form PIF Entered 04/19/2012
    Project Initiation Form PRC Submitted 04/19/2012
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 08/08/2015
    Project Management
    100% Design 100% Package Received 06/16/2014
    100% Design 100% Package Comments to DE 07/29/2014
    25% Design 25% Package Received 04/24/2012
    25% Design 25% Package Received 05/01/2013
    25% Design 25% Package Comments to DE 10/29/2012
    25% Design 25% Package Comments to DE 07/01/2013
    25% Design Design Public Hearing 02/04/2013
    75% Design 75% Package Received 02/19/2014
    75% Design 75% Package Comments to DE 04/04/2014
    Final Design PS&E Received 09/05/2014
    Final Design PS&E to FAPRO 08/05/2015