Project Description:
STOUGHTON- RECONSTRUCTION OF TURNPIKE STREET
Work on this project consists of roadway reconstruction on Turnpike Street in the Town of Stoughton. The project limits are from Pleasant Street Northerly for a distance of approximately 1000 feet. This project is intended to provide a permanent solution to the historical problem of roadway settlement caused by of a vast depth of decomposing subsurface material (peat) which over time has compromised the structural stability of the roadway surface of this targeted segment of Turnpike Street.
Location:
  • Town of Stoughton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $41,007,661.99
    Estimated Total Federal Participating Construction Cost: $42,984,486.30
    District: District 5
    Current Status: 75% Package Comments to DE (as of 06/06/2023 )

    Contracts (2) Progress
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/26/2012
    Project Initiation Form PIF Entered 07/05/2012
    Project Initiation Form PRC Submitted 07/05/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Management
    25% Design 25% Package Received 06/01/2021
    25% Design 25% Package Comments to DE 09/07/2021
    25% Design Design Public Hearing 06/16/2022
    75% Design 75% Package Received 01/31/2023
    75% Design 75% Package Comments to DE 06/06/2023