Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
EASTON- CORRIDOR IMPROVEMENTS ON DEPOT STREET (ROUTE 123), FROM NEWELL CIRCLE TO WASHINGTON STREET (ROUTE 138)
This project is intended to address deteriorated pavement and multi-modal accommodation through reconstruction of the roadway (minor widening) to provide bicycle accommodation in addition to reconstructed sidewalks and extensions. The project is 2 miles in length. A traffic signal is proposed at the Depot Street/Center Street/Porter Street intersection. The project also includes drainage upgrades and new pavements markings and signs.
Location:
  • Town of Easton
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Sean Darling
    Construction Bid Price: $10,134,494.00
    District: District 5

    Contracts (1) Progress
    # 113459 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on a Section of Depot Street (Route 123) 99% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/09/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/01/2012
    Project Initiation Form PIF Entered 08/30/2012
    Project Initiation Form PRC Submitted 08/30/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 11/07/2020
    Project Management
    100% Design 100% Package Received 02/28/2020
    25% Design 25% Package Received 12/04/2014
    25% Design 25% Package Comments to DE 10/28/2015
    25% Design Design Public Hearing 06/12/2018
    75% Design 75% Package Received 03/08/2019
    75% Design 75% Package Comments to DE 06/21/2019
    Final Design PS&E Received 08/24/2020
    Final Design PS&E Received - Resub 1 10/09/2020