ATHOL- CHICOPEE- EASTHAMPTON- NORTHAMPTON- RESURFACING & RELATED WORK AT VARIOUS LOCATIONS
The Interstate 91 portion consists of pavement milling of sections of the north and southbound travel lanes in the cities of Easthampton and Northampton. The pavement milling will reduce the current rutted sections within all travel lanes. The project begins at mile marker 20.8 and continues northerly and terminates at mile marker 26.97. The total length of the project is approximately 6.1 miles. The project shall not include any bridge work or interchange ramp work within the project limits. The Athol (Route 2A) portion consists of overlaying a section South Main Street. The project begins at mile marker 22.75 and continues east and terminates at mile marker 23.17. The total length of the project is approximately 0.42 miles. The project shall not include any bridge work within the project limits. The Chicopee (Route 116) Center Street portion consists of resurfacing of a southbound section from the West Street intersection to the Interstate 91 on-ramp. The project begins at SHLO Station 48%2B20 and continues south and terminates at Station 54+75. The total length of the project is approximately 0.10 miles. The project shall not include any bridge work within the project limits. The work includes the following: pavement milling and resurfacing with HMA pavement, removal of frame and grates, installation of new hook lock frame and grates, installing steel w-beam guardrail, installing painted pavement markings, installing reflectorized slotted pavement markers, traffic controls, and erosion/sedimentation control measures. The milling and paving operations shall be coordinated to pave and mill in each work shift.
Location:
  • Town of Athol
  • City of Chicopee
  • Town of Easthampton
  • City of Northampton
  • Resident Engineer: Mark Joy
    Construction Contract Value: $1,215,309.00
    Construction Bid Price: $1,012,616.75
    Initial Construction Estimate: $917,874.00
    District: District 2

    Contracts (1) Progress
    # 75703 -- Construction Contract
    Micromilling, Resurfacing and Related Work along Sections of South Main Street (Route 2A), Interstate 91 (NB & SB) and Center Street (SB Route 116). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/30/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/16/2012
    Project Initiation Form PIF Entered 05/16/2012
    Project Initiation Form PRC Submitted 05/16/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 09/22/2012
    Project Management
    100% Design 100% Package Received 09/06/2012
    25% Design 25% Package Received 08/24/2012
    75% Design 75% Package Received 08/24/2012
    75% Design 75% Package Comments to DE 09/10/2012
    Final Design PS&E Received 09/06/2012
    Final Design PS&E to FAPRO 09/19/2012