GREENFIELD- INTERSECTION IMPROVEMENTS AT ROUTE 5/10 & CHEAPSIDE STREET
This intersection is poorly aligned, confusing to motorists and has several safety issues. Pedestrian accommodations and sight distance are poor. This project will realign the intersection and add needed turn lanes to improve traffic flow and safety. Other improvements will include new pavement markings, signage and improved pedestrian access.
Location:
  • Town of Greenfield
  • Resident Engineer: John Burek
    Construction Bid Price: $562,866.00
    District: District 2

    Contracts (1) Progress
    # 89761 -- Construction Contract
    Intersection Improvements and Related Work at Route 5/10 (Deerfield Street) and Cheapside Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/29/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/25/2012
    Project Initiation Form PIF Entered 05/25/2012
    Project Initiation Form PRC Submitted 05/25/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 07/25/2015
    Project Management
    100% Design 100% Package Received 04/17/2015
    25% Design 25% Package Received 05/07/2014
    25% Design 25% Package Received 09/04/2014
    25% Design Design Public Hearing 02/12/2015
    75% Design 75% Package Received 11/26/2014
    Final Design PS&E Received 04/17/2015
    Final Design PS&E Received 06/03/2015
    Final Design PS&E Received 06/12/2015
    Final Design PS&E to FAPRO 07/15/2015