Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MONTAGUE- CANALSIDE BIKE PATH & PEDESTRIAN CROSSING IMPROVEMENTS, MONTAGUE CITY ROAD AT SOLAR AVENUE & DEPOT STREET (850 FEET)
This project will provide for accessible and safe bicycle and pedestrian crossings and accommodations for the Franklin County Bikeway. Additional work will include the construction and repair of sidewalks and wheelchair ramps, improved bus stops, pavement markings, signage, pavement narrowing for traffic calming and a possible flashing beacon.
Location:
  • Town of Montague
  • Resident Engineer: Daniel Boucher
    Construction Contract Value: $1,160,947.00
    Construction Bid Price: $989,670.00
    Initial Construction Estimate: $633,000.00
    District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 86118 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Montague City Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/11/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/14/2012
    Project Initiation Form PIF Entered 07/09/2012
    Project Initiation Form PRC Submitted 07/09/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 12/20/2014
    Project Management
    100% Design 100% Package Received 10/08/2014
    100% Design 100% Package Comments to DE 11/05/2014
    25% Design 25% Package Received 09/18/2013
    25% Design 25% Package Comments to DE 12/04/2013
    25% Design Design Public Hearing 02/26/2014
    75% Design 75% Package Received 05/14/2014
    75% Design 75% Package Received 07/09/2014
    75% Design 75% Package Comments to DE 06/24/2014
    75% Design 75% Package Comments to DE 08/18/2014
    Final Design PS&E Received 11/21/2014
    Final Design PS&E Received 12/16/2014
    Final Design PS&E Received 09/15/2015
    Final Design PS&E to Peer Reviewer 11/21/2014
    Final Design Peer Review Comments to DE 12/10/2014
    Final Design PS&E to FAPRO 12/17/2014
    Final Design PS&E to FAPRO 09/30/2015