Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SANDISFIELD- BRIDGE MAINTENANCE, S-03-030, ROUTE 8 (SOUTH MAIN STREET) OVER SILVERNAIL BROOK
This contract is for federal-aid eligible bridge maintenance activity at various locations throughout the District.
Location:
  • Town of Sandisfield
  • Resident Engineer: Joseph Mastroianni
    Construction Contract Value: $305,536.00
    Construction Bid Price: $275,215.00
    Initial Construction Estimate: $246,200.00
    District: District 1

    Contracts (1) Progress
    # 77397 -- Construction Contract
    Bridge Deck and Substructure Repair (S-03-030) (Steel) - Route 8 (South Main Street) over Silvernail Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/09/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/26/2012
    Project Initiation Form PIF Entered 06/28/2012
    Project Initiation Form PRC Submitted 06/28/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 05/04/2013
    Project Management
    Final Design PS&E Received 01/23/2013
    Final Design PS&E to FAPRO 04/25/2013