Project Description:
FITCHBURG- SAFE ROUTES TO SCHOOLS (SOUTH STREET ELEMENTARY SCHOOL)
Recommended improvements: Installation of sidewalks, wheelchair ramps, crosswalk striping and warning signs.
Location:
  • City of Fitchburg
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Ryan Davison
    Construction Bid Price: $1,177,664.75
    District: District 3

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 85766 -- Design -- Highway
    Work will consist of providing school assessments and preliminary and final engineering design and construction phase services to the Highway Engineering Division for the 2014 Final
    # 97597 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on Sections of South Street, Electric Avenue and Adjacent Streets (Safe Routes to School – South Street Elementary Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/10/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/26/2012
    Project Initiation Form PIF Entered 06/26/2012
    Project Initiation Form PRC Submitted 07/18/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 08/27/2016
    Project Management
    100% Design 100% Package Received 04/11/2016
    100% Design 100% Package Comments to DE 05/17/2016
    25% Design 25% Package Received 01/04/2016
    25% Design Design Public Hearing 02/24/2016
    75% Design 75% Package Received 01/04/2016
    75% Design 75% Package Comments to DE 03/23/2016
    Final Design PS&E Received 08/03/2016
    Final Design PS&E Received 08/16/2016
    Final Design PS&E to FAPRO 08/22/2016