Project Description:
WINTHROP- RECONSTRUCTION & RELATED WORK ALONG WINTHROP STREET & REVERE STREET CORRIDOR
This project will include a complete street which will inlcude pavement reconstruction and reclamation, sidewalk reconstruction and intersection improvements at key locations along the corridor. Improvements to the bicycle and pedestrian conditions will be implemented.
Location:
  • Town of Winthrop
  • Construction Begins: Summer 2023
    Resident Engineer: Tibebu Gashaw
    Construction Bid Price: $7,501,557.00
    District: District 6

    Contracts (1) Progress
    # 122603 -- Construction Contract
    Reconstruction & Related Work along Winthrop Street & Revere Street Corridor 20% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/12/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/26/2012
    Project Initiation Form PIF Entered 06/26/2012
    Project Initiation Form PRC Submitted 07/02/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 06/24/2023
    Project Management
    100% Design 100% Package Received 10/24/2022
    100% Design 100% Package Comments to DE 11/29/2022
    100% Design 100% Plans Approved 01/17/2023
    100% Design 100% Plans Complete 01/17/2023
    25% Design 25% Package Received 02/26/2019
    25% Design 25% Package Comments to DE 12/23/2020
    25% Design Design Public Hearing 04/22/2021
    75% Design 75% Package Received 07/30/2021
    75% Design 75% Package Comments to DE 09/02/2021
    75% Design 75% Package Received - Resub 1 02/15/2022
    Final Design PS&E Received 03/17/2023
    Final Design PS&E Received - Resub 1 04/14/2023
    Final Design PS&E Received - Resub 2 05/03/2023