PAXTON- RECLAMATION ON ROUTE 31 (HOLDEN ROAD)
The project extends from Grove Street to the Holden TL (0.8 miles) and involves pavement reclamation, construction of 1,000’ of new sidewalk and drainage improvements.
Location:
  • Town of Paxton
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Peter Kurt
    Construction Bid Price: $3,086,193.50
    District: District 3

    Contracts (1) Progress
    # 105264 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Route 31 (Holden Road) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/06/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/03/2012
    Project Initiation Form PIF Entered 07/03/2012
    Project Initiation Form PRC Submitted 07/18/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 07/28/2018
    Project Management
    100% Design 100% Package Received 09/11/2017
    100% Design 100% Package Comments to DE 11/16/2017
    25% Design 25% Package Received 03/20/2014
    25% Design 25% Package Comments to DE 02/18/2015
    25% Design Design Public Hearing 05/07/2015
    75% Design 75% Package Received 01/25/2016
    75% Design 75% Package Comments to DE 11/07/2016
    Final Design PS&E Received 05/14/2018
    Final Design PS&E to Peer Reviewer 05/15/2018
    Final Design Peer Review Comments to DE 06/11/2018
    Final Design PS&E Received - Resub 1 07/12/2018